70 EAST CEDAR STREET

The best is yet to come.

Scope of Project

LINING THE SEWER DRAINS,
VENT STACKS, AND STORM DRAINS

70 East Cedar – Phase 1
Estimated Drain and Vent Pipe Lining Schedule

Over the course of the next year Nu Flow Midwest will be working with Althoff Industries to rehabilitate the drain and vent pipes behind the walls in each of your units. We will be isolating and working on a single combination of sewer and vent stack, from top to bottom, at a time. To understand where we will be at any given time we have put together the below tentative schedule.

One of the biggest advantages epoxy pipe lining has over pipe replacement is that we don’t have to access the majority of the pipe to rehabilitate it. One of the hardest parts of our jobs, though, is not having access to the entire length of each pipe which forces us to deal with a lot of unknown. We assume some pipe will be better than other so this schedule may adjust from time to time as the project progresses. If there is any deviation from this plan our project manager, Dean Wheatley, will communicate those changes to all residents. This schedule will also be maintained here so you can check for yourself at any time.

Reference Name (from attached diagram) Affected Room Type Description Estimated Start Date Estimated Completion Date Before & After Videos
VS-1 Bathroom Southwest Corner Bathroom June 27, 2016 July 22, 2016
Notes:
VS-2 Bathroom Center West Bathroom July 25, 2016 August 5, 2016
Notes:
VS-3 Bathroom Northwest Bathroom August 15, 2016 September 2, 2016
Notes:
VS-10 Butler’s Pantry can find on this page Sink/Bar in Butler’s Pantry September 5, 2016 September 23, 2016
Notes:
VS-4 Kitchen Kitchen Sink September 26, 2016 October 14, 2016
Notes:
RD-1 TBD Roof Drain TBD TBD
Notes:
RD-2 TBD Roof Drain TBD TBD
Notes: