222 E Pearson

The best is yet to come.

Scope of Project

PIPE REHABILITATION AND PREVENTATIVE MAINTENANCE

REPAIR AND REPLACE VENT STACKS WITH INSERTS

NO INVASIVE REPAIR WORK TO YOUR CONDO

NO LEAKS

70 East Cedar – Phase 1
Estimated Drain and Vent Pipe Lining Schedule

Over the course of the next year Nu Flow Midwest will be working with Althoff Industries to rehabilitate the drain and vent pipes behind the walls in each of your units. We will be isolating and working on a single combination of sewer and vent stack, from top to bottom, at a time. To understand where we will be at any given time we have put together the below tentative schedule.

One of the biggest advantages epoxy pipe lining has over pipe replacement is that we don’t have to access the majority of the pipe to rehabilitate it. One of the hardest parts of our jobs, though, is not having access to the entire length of each pipe which forces us to deal with a lot of unknown. We assume some pipe will be better than other so this schedule may adjust from time to time as the project progresses. If there is any deviation from this plan our project manager, Dean Wheatley, will communicate those changes to all residents. This schedule will also be maintained here so you can check for yourself at any time.

VIEW SCHEDULE BELOW TO
FIND OUT WHEN WORK
WILL BE DONE ON YOUR FLOOR.

Building Riser Being Worked On Floors Affected Affected Unit(s)
If your unit does not appear in this list then all work will be performed from the inside of the pipe
First Day of Access Last Day of Access Comments Watch the Before and After Video
PS1 25 2508, 2509 Oct 26 Nov 9 Before
After
PS1 20 2008, 2009
PS1 15 1508, 1509
PS1 9 908, 909
PS1 3 308, 309
PS14 25 2508 Nov 4 Nov 18
PS14 20 2008
PS14 15 1508
PS14 9 908
PS14 3 308
PS15 25 2506 Nov 11 Nov 25
PS15 20 2006
PS15 15 1506
PS15 9 906
PS15 3 306
PS13 25 2506 Nov 24 Dec 8
PS13 20 2006
PS13 15 1506
PS13 9 906
PS13 3 306